| Governing standard |
ASTM / ASME / EN / customer specification and required edition. |
Confirm scope includes the requested welded pipe manufacturing route. |
| Grade / UNS |
Exact designation belonging to the selected standard. |
Verify chemistry and mechanical requirements on the MTC against that standard. |
| NPS / DN |
Nominal pipe size or DN; add drawing-controlled OD where required. |
NPS is a pipe-size designation, not automatically the actual outside diameter. |
| Wall thickness |
Schedule designation such as 5S / 10S / 40S / 80S where applicable, or actual nominal wall. |
Check dimensional standard and project tolerance requirements. |
| Length |
Random, fixed, cut length or project-specific tolerance. |
Confirm usable length, end allowance and packing limitations. |
| Weld / manufacture |
Straight seam, electric-fusion welded, standard class or other route when specified. |
Confirm the chosen standard permits and defines the requested manufacturing route. |
| Heat treatment |
Condition required by the material specification or project document. |
Do not assume annealed / unannealed status from appearance or grade alone. |
| Surface condition |
Pickled, passivated or other project-controlled finish when required. |
Agree surface acceptance, contamination controls and any additional treatment. |
| Ends |
Plain, beveled or other drawing / piping-spec requirement. |
Confirm angle / land / burr requirements when fabrication or welding depends on them. |
| Inspection & documents |
NDE / hydrostatic or electric test, dimensional checks, PMI if required, MTC and traceability. |
State the acceptance plan before purchase; do not add tests after shipment. |